  • The IGST 4_2 is planned to be run on the ETB with MEB EM2 on April 2018 
  • ISM doc. to be delivered at MOC before 
  • Procedure/sequence to be delivered at MOC before 
  • MEB EM2 with IDB 4.3.3 will be used on ETB during test, however the procedures/sequences must be written using the PFM IDB 4.3.3 version (indicating clearly where there are discrepancies between the two versions).
  • Presence of 1-2 max. people from RPW at ESOC during test is strongly recommended by MOC

...

In terms of command/control the RPW IDB (V4.3.3) is the same for EM1, EM2 and PFM, nevertheless the FDIR triggering threshold values can be different between the 3 models! This has to be taken account when validated the test results.

Moreover there is no SCM and PA-HF/ANT sensor on the ETB/RPW-EM2 setup, in consequence the during the IGST:

  • Switching ON SCM shall be prohibited
  • BIAS HV shall be not used
  • Switching ON PA HF shall be prohibited


Info
titleNOTE
According to Sylvain Lodiot (see comments at the bottom of the page) the corresponding prohibited TCs in the sequences must be clearly indicated with the  [not for the EM2 on the ETB] comment.

Status of the data package 

...

ISM status

VersionStatusComment
1.0DeliveredDelivered with the datapack 1.0
1.1In preparation (required updates due to changes in SQ between data pack 1.0 and 1.1)

To be delivered with datapack 1.1.

...

VersionStatusDelivery dateComment
1.0Delivered

 

Delivered to Sylvain Lodiot (MOC). See feedbacks in

Jira
serverjira-lesia.obspm.fr JIRA
serverIdcb08a004-0694-3237-bcb1-3125e3ed9bc0
keyROCOPE-81

1.1To be delivered

Expected for  

To be delivered to Sylvain Lodiot (MOC)

...

How the
QuestionAnswerSeverityComment
Do the sequences related to the routine operations (Bias sweeping, calibrations, etc.) will be tested during the IGST?
Low





...