The ROC and CNES are in charge of preparing the sequence of TCs relative to the instrument modes, to be operated during the deployements. The sequence of TCs that will drive the deployements them-selves will be delivered by the RPW antenna team.
Overall timeline
View file | ||||
---|---|---|---|---|
|
At SOLO level
The following operations will be then performed at the platform level.
...
The table gives the timeline for the first ANT deployement, assuming that the RPW configs. will be the same for the 3 ANTs.
Start Time | Duration | ANT state | RPW state | Comment |
---|---|---|---|---|
T1 - 10 minutes | 9 min | The ANT1 is stowed | RPW is switched on and set to the ANT pre-deployement specific config. |
|
T1 - 1 minutes | 9 min | The ANT1 is stowed | RPW is set to the ANT deployement specific config. |
|
T1 + | ||||
T1 + | ||||
Orbitography
TBD
Operation Constraints
...