The ROC and CNES are in charge of preparing the sequence of TCs relative to the instrument modes, to be operated during the deployements. The sequence of TCs that will drive the deployements them-selves will be delivered by the RPW antenna team.

Overall timeline

View file
nameprocedure_ant_depl.docx
height250

At SOLO level

The following operations will be then performed at the platform level.

...

The table gives the timeline for the first ANT deployement, assuming that the RPW configs. will be the same for the 3 ANTs.

Start TimeDurationANT stateRPW stateComment
T1 - 10 minutes9 minThe ANT1 is stowedRPW is switched on and set to the ANT pre-deployement specific config.
  • This config shall include 3 to 5 minutes of "Galaxy mode" for THR
T1 - 1 minutes9 minThe ANT1 is stowedRPW is set to the ANT deployement specific config.
  • Specific SBM1 mode (will it require to change Packet Store?)
T1 +



T1 +














Orbitography

TBD

Operation Constraints

...