Page to centralize information about the activities related to the SVT1.
ROAD MAP TO SVT1
The main milestones towards the SVT1 are reported below.
The information about the description and expected delivrables for the SVT1 can be found in SVT1.
Time period | Activity | Deliverables |
---|---|---|
September 2018 | Discussion with each team (THR, TDS, LFR, Bias, SCM, DBS/DAS and CNES) to define the instrument configurations for each of the identified RPW operations in-flight during NECP and CP (including the configurations to be planned in the CP MLP and contingency cases) | Results of the discussion shall lead to the release of a first draft of the RPW flight configurations description document (FCDD), as well as the RPW operation plans (ROP) - 1 by operation - on the end of September 2018. These documents will have to be distributed to the PI, CNES and Lead CoI teams |
01st to 15th of October 2018 | Planned a telecon to discuss all together about the FCDD and ROP. | The telecon shall lead to the signature by the RPW PI, instrument scientist, ROC project manager and Lead CoIs of the first issue of the FCDD for mid-October 2018. |
mid-October to end of November 2018 | Identify single TC not in SQ Write and test on the LESIA GSE the TC sequences to set the instrument with the FCDD configurations. | TC sequences report |
Mid-December 2018 | Deliver the SVT1 DATA PACK to MOC | SVT1 DATA PACK |
ACTIVITY STATUS
Children Display |
---|
RESOURCES
Document templates to be filled by teams: