RW filtering at this step ? - probably when EMC with platform
Instead of 80 min per inter-instrument step, only need for ~5 min
2. RPW PAS filtering tune campaign (RPW-7)
LFR 2 config. : ENABLE then DISABLE PAS-filtering
PAS ON
Action EL : Organize a telecon with PAS team about RPW-7
Jira
showSummary
false
server
jira-lesia.obspm.fr JIRA
serverId
cb08a004-0694-3237-bcb1-3125e3ed9bc0
key
ROCOPE-226
3. Discussion of cruise phase configuration : low rate config
ROC will keep the two first configurations. if SBM1 data can be retrieve, config 2 will be chosen. Else config 1.
No time left to discuss galaxy and default configuration
4. Action-items, organization and planning
First draft of Commissioning procedures will be sent to MOC before
A overview document will be written by ROC summarizing all the configurations (commissioning + CP) for each step and each subsystem. Approval by each lead CoI will be requested