Page properties | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ||||||||||||||
|
Summary
Preparation of the SVT1 datapackage release for RPW.
The SVT1 campaign is expected to occur between Feb. to May 2019 (TBC).
Main features of the
releaseSVT1 datapackage
- Upgraded Upgrading and validation of the RPW flight procedures from SVT0 IGST42 datapackage
- New RPW flight procedures related to the instrument commissioning and cruise phase operations.
- Upgraded version Upgrading of the RPW ISMPreparation and validation
- First issue 1.0 of the RPW flight procedures for LEOP/NECP operations
- configuration description document (FCDD)
Planning
- A first set of RPW flight procedures for SVT1 is planned to be delivered by email to Sylvain Lodiot (MOC) on mid-October 2018.
- The full SVT1 data package will have to be delivered before .
JIRA issues related to the SVT1 datapackage
Jira | |||||||
---|---|---|---|---|---|---|---|
|
|