Time period | Activity | Deliverables |
---|---|---|
September 2018 | Discussion with each team (THR, TDS, LFR, Bias, SCM, DBS/DAS and CNES) to define the instrument configurations for each of the identified RPW operations in-flight during NECP and CP (including the configurations to be planned in the CP MLP and contingency cases) | Results of the discussion shall lead to the release of a first draft of the RPW flight configurations description document (FCDD), as well as the RPW operation plans (ROP) - 1 by operation - on the end of September 2018. These documents will have to be distributed to the PI, CNES and Lead CoI teams |
01st to 15th of October 2018 | Planned a telecon to discuss all together about the FCDD and ROP. | The telecon shall lead to the signature by the RPW PI, instrument scientist, ROC project manager and Lead CoIs of the first issue of the FCDD for mid-October 2018. |
mid-October to end of November 2018 | Identify single TC not in SQ Write and test on the LESIA GSE the TC sequences to set the instrument with the FCDD configurations. | TC sequences report |
Mid-December 2018 | Deliver the SVT1 DATA PACK to MOC | SVT1 DATA PACK |
ACTIVITY STATUS
Children Display |
---|
RESOURCES
Document templates to be filled by teams: