Goals
- Discuss about the configurations chosen by each sub-system teams for each step of the commissioning. Those configurations have to be delivered to MOC before
Date
Attendees
- Eric Lorfevre
- Jean-Michel Travert
- Antonio Vecchio
- Diane Berard
- thomas chust
- rodrigue piberne
- Erik Johansson
- Unknown User (avaivads)
- Jean-Yves Brochot
- Jan Soucek
- Unknown User (mkretzschmar)
Agenda
The discussion is based on the attached presentation detailing the different issues.
- State of reception of documents detailing configuration for each step and each sub-system
- Discussion on each commissioning step and validation by each team
- Discussion of cruise phase configuration : low rate config
- Action-items, organization and planning
Global remark :
- SBM1 is requested for each commissioning operation but is not mandatory. To be checked with MOC to be sure that SBM1 data can be downlinked on ground. If not, Normal mode will be used for each sub-system.
Discussion items
Item | Notes | Actions-items |
---|---|---|
| Every team sent to ROC all the documents before the meeting. The config for reaction wheels filtering is missing | |
2. First RPW switch-on and in-flight SFT (RPW-1) |
| |
2. I-Boom deployment (RPW-2) |
→ THR will lead the overall timeline of the deployment - THR requests to have 3 PA HF ON? | |
2. ANT deployment (RPW-3) | We asked for 3h duration : 3 rotations of 1h
→ THR will lead the overall timeline of the deployment THR requests to have 3 PA HF ON (cf. action EL about risk with PA heating above) | |
2. ANT calibration rolls (RPW-4) |
| |
2. SCM calibration operation (RPW-5) |
| |
2. In-flight inter-instrument interference campaign (RPW-6) |
| |
2. RPW PAS filtering tune campaign (RPW-7) |
| Action EL : Organize a telecon with PAS team about RPW-7 |
3. Discussion of cruise phase configuration : low rate config | ROC will keep the two first configurations. if SBM1 data can be retrieve, config 2 will be chosen. Else config 1. No time left to discuss galaxy and default configuration | |
4. Action-items, organization and planning |
| Action DB+AV : prepare the configuration document |