- RPW L1R/L2 data processing status at LESIA
See 200423_ROC_Telecon21_NQN.pdf
- Anomaly report
- SCM SURV-CWF L2 data: problem with SAMPLING_RATE (to be fixed in SCMCAL 0.11.0)
- Anomaly reported by LFR concerning BP1 L2 skeletons V06 → RCS teams must only commit/push CDF skeleton tables (ASCII) in the "rcs" branch of the DataPool Git repo.
- Proposal for RCS update at LESIA and L1R/L2 generation cadence ?
- RCS update every TBD weeks or months ? After each delivery ?
- It is discussed to not share (even with CoIs) L1/L2 CDFs which are not at least well time-stamped (to be discussed at the next ROB telecon)
- The "GO" to (re)generate first L2 to be delivered to the CDAG at ESAC will be discussed on next ROB telecon
- Teams need to be able to look at "failed" L1R/L2 CDF processing. Xavier and Quynh Nhu will put "failed" L1R/L2 CDF in specific directories accessible to the teams (same for log files)