Agenda
- RPW data processing - Status overview
- On-going & future developments
- Documentation
- Planning
- Next RCS telecon
- AOB
Discussion items
Item | Notes | Action-items |
---|
1. | - L0/L1/HK data production
- L2 data & L3 summary plots production
- Data sharing
- Data public release
- HFR survey data L1/L2 have been reprocessed to fix a serious problem with Epoch values
- Delivery to ESAC has been stopped. Will be restarted (data before 30/01/2021 and 13/03/2021 will not be published)
| - By Xavier Bonnin before : To plan a meeting with Antonio, Jeremy and Xavier about TNR-HFR summary plot
|
2. | - TDS WF resizing
- SBM data production
- MODS change in CDF skeletons & Data release traceability
- New L3 data
- Preparation of ESAC delivery for VHT L3 CDF. Waiting for reply from ESAC.
- Science quality
- No progress
- Setting QUALITY_BITMASK for L1 CDF will have to be ended on Sept. 2021
- Summary plots
- Adding HK CDF dataset for:
- LFR KCOEFF and Parameters dump (suspended)
- SBM1 HK (suspended. Required ?)
| |
3. | - DPDD
- Issue 1.4 in preparation (includes Bias L3 VHT data product + minor skeleton updates)
- RCS ICD
- New draft 1.5 submitted for feedback
| |
4. | - Next RPW data re-processing should be scheduled on Fall 2021 (if possible before nominal phase)
|
|
5. | - Next RCS telecon is scheduled on September 16 at 2PM
|
|
6. | |
|
Previous notes
(2021-05-05) RCS telecon#28
Attached items