Preparation of the 0th E2E test data package for RPW:

  • Related procedure/sequence to be delivered at MOC before  (SOC in copy). 
  • Related STP IORs to be delivered at SOC before .
  • SOC will send test specification on March-April 2018.
  • MEB PFM IDB 4.3.3 will be used during test.
  • The 0th E2E test is planned to be run on April-May 2018 at SOC.
  • Presence of people from RPW at ESAC is not required (TBC)

Details of the test can be found here: https://rpw.lesia.obspm.fr/roc/data/private/devtest/soc/E2E-0/

Input data files sent by SOC are available here: https://rpw.lesia.obspm.fr/roc/data/private/devtest/soc/E2E-0/ (restricted access)

Interlocutors are:

  • Sylvain Lodiot at MOC
  • Chris Watson at SOC



Main features of the release

  1. Release of the set of flight procedures/sequences to run the IOR related to the LTP SOWG10 exercice timeline (see https://solarorbiter.esac.esa.int/soopkitchen/#/planning/SOWG10_LTP_Exercise)
  2. Release of the STP IORs as expected by SOC during operations (see IORS ICD).

Description of the data package

  • Set of STP IORs for the 0th E2E CP test
  • Associated procedures/sequences (already delivered in the IGST 4_2 datapack)
  • README.rst with a description of the content
  • CHANGELOG.rst, with a history of modifications

The name of the data package must be delivered as a zip file, named as: RPW_0thE2E_DATAPACK_IssueXX_RevYY.zip, where XX and YY are the issue and revision of the data pack.

Status of the data package 

Sequences status

The sequences required to run the 0th E2E test are delivered to the MOC via the IGST data package.

See RPW IGST 4_2 DATAPACK RELEASE for a complete list of the sequences status.

IOR status

It is planned to deliver all of the STP IOR for the SOWG10 LTP exercice timeline.

ContentStatusComment
Set of STP IORs for the SOWG10 LTP exercice planningFirst draft to be delivered before end of March 2018.

To be checked:

  • Do the IORs cover the LTP time range?
  • Do the IORs are consistent with the LTP RPW modes?
  • Do the IORs are in agreement with the TMC constraints?
  • Do the IORs are valid according to the IDB (4.3.3 PFM)?
  • Do the IORs are valid according to the IOR ICD?
  • Do the SOC GFTS is up-and-running?


Expected documentation

TBW

TBW