Agenda
Content of the RPW_NECP.xlsx
Action-items and planning
Next operation telecon
AOB
Discussion items
Time
Item
Who
Notes
First RPW switching-on
A first "RPW-0" operation shall be planned prior to the iBoom and ANT deployements.
This operation shall consist of switching-on the instrument and perform a SFT-like test to check the instrument behavior.
Details have to be defined, but the operation should take around 1h20 (typical duration of a SFT test) and should be planned at least 24h before the beginning of the deployement operations (to let the time to the RPW team to analyze and validate the first switching-on)
As a remider, the iBoom and ANT depl. are planned during the LEOP phase (the 7 days after launch)