Information about the I-Boom deployment operation during the LEOP.
Working Group Members
RPW sub-system teams will also contribute to define the RPW modes to be set during the deployement.
Contact at MOC
- Sylvain dot Lodiot at esa dot int
Operation timeline and instrument configuration overview
Fig. 1. I-Boom operation timeline
In this phase, RPW measures the noise of the platform. RPW is set in a single specific configuration for I-BOOM deployment. Measurements will be also taken during the first and last 10 minutes before and after the IBOOM deployment. RPW in SURVEY_BURST SCIENCE submode with both spectral modes (all frequencies for B) and waveforms. The instrument is expected to be switched off before and after the operation.
Minimal requirements:
- THR: B field on channel 1 and E on channel 2 (all frequencies, max freq resolution).
- LFR: spectral mode maximum frequency resolution.
- No TDS.
Maximal requirements
- THR: B field on channel 1 and E on channel 2 (all frequencies).
- LFR: spectral mode maximum frequency resolution, B waveforms at 256 Hz.
- TDS snapshots
The table below gives the organization of the operation stages and associated timing.
Activity | Step | Description | Time since beginning |
---|---|---|---|
Instrument initialization | A | RPW switch on and go to I-BOOM mode/configuration | 0 min |
I-BOOM deployment data acquistion and visualization | B | Beginning of the I-BOOM deployment | 10 min |
I-BOOM deployment data acquistion and visualization | C | End of the I-BOOM deployment | 130 min |
Instrument switch off | D | RPW switch off | 140 min |
The table below gives the RPW modes and configurations (i.e., states) expected for each step of the operation timeline.
First step | Last step | RPW configuration | Duration | Comment |
---|---|---|---|---|
A | D | RPW_NECP_IBOOM-DEPLOY_CONFIG1 | 140 min. | A single configuration will be used during the entire operation timeline. |
Orbitography
TBW
Success criteria
TBW
Operational constraints, assumptions and dependencies
Resources allocation
Power consumption allocation
TBW
Telemetry allocation
900 kbps available for platform + payload.
Details of allocation are TBD
Instrument-related constraints, assumptions and dependencies
The DPU SCIENCE SBM_DETECTION submode can be applied on-board during NECP, but there is not guarantee that the resulting SBM data stored on the SSMM can be downlinked to ground by MOC during this phase. (Note that the dump of the SBM data by the DPU can be forced by TC, since in the nominal case the transfer of data from the DPU SBM buffers to the SSMM is only done when an event is detected on-board.)
Spacecraft-related constraints, assumptions and dependencies
TBW
Ground constraints, assumptions and dependencies
TBW
Related resources
Meeting Notes
Open Actions Items
Attached Items
- procedure_IBOOM_depl.docx
- RPW-related operations during LEOP – The SSMM will finally available during these operations.
- TDS configuration :
- LFR configuration :