Pierre-Luc suggests to re-run these tests but with shortest/longest integration times for TNR
Resulting analysis and data will have to be sent to Kamel
THR FSW patching test/Validation
Kamel agrees to come a week at LESIA to support test/validation of the patched FSW
According to Claudine, LESIA can pay for travelling and hostelling
Support of ROC team may require if new tests are needed on EM2 (only for band A deltatime issue). For other issues, activities can be performed on the THR GSE
QAP support
CNES (Charles Dixon) can provide a ponctual and consulative support, but not an effective one
To see if support from ex-Nexeya is required or not
THR FSW documentation upgrade
Modifications in the FSW doc. might be minor
Needs of change to be identified (with the support of Charles Dixon)
Not done by Kamel
From the ROC point of view, the final datapack to be sent to ESA should contain at least the updated version of (N.B. the exact list of doc. may be refined by THR team with the help of Charles Dixon):
THR FSW specification doc.
THR manuel doc.
FSW test/validation report
THR team to think about who will update the documentation related to FSW patching
2.
According to Moustapha, it will be not possible for THR team to deliver FSW patch before end of June as expected
Xavier thinks that it should be still possible to deliver FSW patch before end of July. It must however be confirmed with Philippe Plasson
Moustapha and Pierre-Luc will contact Kamel to see with him if the timing is realistic or not (especially concerning the delivery of the documentation)
Xavier Bonninto see with Philippe Plasson if end of July is OK to receive FSW patch from THR (before )
Moustapha to confirm to Xavier Bonnin if it is possible to deliver THR FSW patch to Philippe before end of july (before )
3.
Next FSW upgrade meeting planned on June 25 at 10AM (CEST)