1. | - LFR
- ASM bug has been solved, but S/W crashes (new computation in S/W seems to be too heavy for CPU load. Work is still in progress
- QAP support:
- Required support needs to be refine with help of the CNES, as well as budget
- May be approx. 5-6 days of NEXEYA support
- Joined effort with LESIA is probably not needed, since the degrees of quality support should be not the same (less for LESIA)
- TDS
- A new version of the TDS software will delivered
- TDS should be OK to deliver a FSW image before mid-July 2021
- Upgrades seem to be OK (need verifications)
- Not important changes, increases by few bytes the software size
- LeeRoy thinks it will be OK to deliver corresponding C-SGSE scripts to ROC by the end of August.
- THR
- FSW upgrades
- Science algorithm of new THR FSW has been tested by Pierre-Luc
- FSW tests
- C-SGSE scripts RPWDPU-1984_Load_EEPROM1_RpwThrApp_V3_6_1_0 and RPWDPU-1984_Load_EEPROM2_RpwThrApp_V3_6_1_0 available on RPW-AIT2AI
- Scripts to be run by ROC
- Kamel will be at LESIA from July 5 to 9 to test and finalize the THR patch. It can be good that both ROC and DAS teams are available if required.
- ROC will try to see with Simone Thjis if it is possible to test the execution of the C-SGSE scripts before the Kamel's arrival (TBC)
- New TNR tests on EM2 perfomed by ROC at LESIA. Data sent to Antonio
- QAP support
- Light support needed for LESIA.
- THR team will see with CNES about quantifying support from NEXEYA and the impact on the FSW upgrade on documentation.
- Planned a discussion about documentation between THR team and Charles Dixon, if possible, during the week when Kamel is at Meudon.
- Documentation:
- Kamel might write the documentation
- What about THR test plan ? See with ESA (if all tests in plan are not run, it shall be justified)
- If everything is OK, new THR FSW image might be delivered before mid-July
- ROC
- Will support THR team for the tests run when Kamel will be here
- Still need to write formal plan in preparation to in-flight patching operation
- MOC/SOC will have to be informed if current planning is changed
- Main activities are still planned on Sept/October (retrieve C-SGSE scripts, test on EM2 and convert into MDOR/PDOR)
| - ROC
- See slides from Diane (pdf)
- Switch back to EEPROM1 (in case of problem) must be done one week before E-GAM. We have about one month to check the good behavior of the patches on EEPROM2
- Datapack
- TDS FSW UM needs updates → update before Sept. 24
- Send a first version of the datapack to TDS/THR/DAS/CNES teams for review before delivering (send a copy to FSW team at CNES → Benoit Fresoul)
- LFR
- All bugs have been fixed (ASM, CPU)
- Not big change in algo
- S/W load slightly higher (few %)
- S/W size will be estimated (may be slightly bigger)
- Start test phase
- Should be able to deliver a datapack to LESIA and CNES around mid-decembre
- What about static analysis? To be discussed with Charles
- What about coverage analysis? Heavy and long process. Running tests only could be enough. (Last coverage report indicated 90% for lines coverage and 85% for branch coverage. Quite above requirements)
- No IDB impact → To be formally confirmed with Philippe and LeeRoy
| - Xavier to generate and share CDF L1/HK for SFT on EM2
- Diane ROC (Xavier/Diane) to write a "RPW FSW patching report" detailling the tests results - To be joined with teams' documents to the datapack delivered to ESA
- Diane to write operation activity plan (in preparation to on-board patching)
- Diane and Xavier to create PDOR/MDOR
- ROC to prepare the datapack (send a preliminary version to teams for review)
|
2. | - Operation activities (timeline, roles and validation) must be refined with MOC. Especially, it must be discussed about the presence of RPW people at MOC during the operation.
| 2. | - TDS/THR FSW images delivered on mid-July 2021 to DAS team
- DAS team to deliver to ROC C-SGSE scripts (deadline mid-september 2021)
| - LFR team to refine the date of delivery for its patch in 2022 - End of 2021
|