Switch back to EEPROM1 (in case of problem) must be done one week before E-GAM. We have about one month to check the good behavior of the patches on EEPROM2
Datapack
TDS FSW UM needs updates → update before Sept. 24
Send a first version of the datapack to TDS/THR/DAS/CNES teams for review before delivering (send a copy to FSW team at CNES → Benoit Fresoul)
LFR
All bugs have been fixed (ASM, CPU)
Not big change in algo
S/W load slightly higher (few %)
S/W size will be estimated (may be slightly bigger)
Start test phase
Should be able to deliver a datapack to LESIA and CNES around mid-decembre
What about static analysis? To be discussed with Charles
What about coverage analysis? Heavy and long process. Running tests only could be enough. (Last coverage report indicated 90% for lines coverage and 85% for branch coverage. Quite above requirements)
No IDB impact → To be formally confirmed with Philippe and LeeRoy
Xavier to generate and share CDF L1/HK for SFT on EM2
Diane to write a "RPW FSW patching report" detailling the tests results - To be joined with teams' documents to the datapack delivered to ESA
Diane to write operation activity plan (in preparation to on-board patching)
Diane and Xavier to create PDOR/MDOR
ROC to prepare the datapack (send a preliminary version to teams for review)
2.
Operation activities (timeline, roles and validation) must be refined with MOC. Especially, it must be discussed about the presence of RPW people at MOC during the operation.
LFR team to refine the date of delivery for its patch in 2022 - End of 2021
3.
Next meeting planned on Novembre 15 at 10AM (CET) to with teams