Page to centralize information about the activities related to the SVT1.


ROAD MAP TO SVT1

The main milestones towards the SVT1 are reported below.

The information about the description and expected delivrables for the SVT1 can be found in SVT1.

Time periodActivityDeliverables
September 2018Discussion with each team (THR, TDS, LFR, Bias, SCM, DBS/DAS and CNES) to define the instrument configurations for each of the identified RPW operations in-flight during NECP and CP (including the configurations to be planned in the CP MLP and contingency cases)Results of the discussion shall lead to the release of a first draft of the RPW flight configurations description document (FCDD), as well as the RPW operation plans (ROP) - 1 by operation - on the end of September 2018. These documents will have to be distributed to the PI, CNES and Lead CoI teams

01st to 15th of October 2018

Planned a telecon to discuss all together about the FCDD and ROP.The telecon shall lead to the signature by the RPW PI, instrument scientist, ROC project manager and Lead CoIs of the first issue of the FCDD for mid-October 2018.
mid-October to end of November 2018

Identify single TC not in SQ

Write and test on the LESIA GSE the TC sequences to set the instrument with the FCDD configurations.


Mid-December 2018Deliver the SVT1 DATA PACK to MOCSVT1 DATA PACK

ACTIVITY STATUS

RESOURCES