Goals

  • Discuss about the configurations chosen by each sub-system teams for each step of the commissioning. Those configurations have to be delivered to MOC before  

Date

Attendees



Agenda

The discussion is based on the attached presentation detailing the different issues.

  1. State of reception of documents detailing configuration for each step and each sub-system
  2. Discussion on each commissioning step and validation by each team
  3. Discussion of cruise phase configuration : low rate config
  4. Action-items, organization and planning


Discussion items

Item

Notes

Actions-items

  1. State of reception of documents detailing configuration for each step and each sub-system
Every team sent to ROC all the documents before the meeting. The config for reaction wheels filtering is missing
  1. LFR team needs to provide the inputs for reaction wheels filtering test before  

2. First RPW switch-on and in-flight SFT (RPW-1)

  • based on standard SFT as for ground 
  • tools : ROC tools as I/F with MOC
  • SFT configuration description can be found in C-SGSE script and run doc. only  


  • Action JMT : to provide any input for this operation. Especially send the last version of the SFT C-SGSE script and doc.

2. I-Boom deployment (RPW-2)

  • LFR — 1 config over all the operation 
  • TDS — 1 config.  over all the operation (mag. data only)
  • THR — 2 config.  = 1 before/after (10 min.) + 1 during deployment.
  • BIAS — OFF

→ THR will lead the overall timeline of the deployment

- THR requests to have 3 PA HF ON?
- ANT PZ might be deployed before the I-boom in the current scenario 

  • Action EL —> check if there is no risk when ANT are stowed (PA heating)

2. ANT deployment (RPW-3)

  • LFR - 1 config. over all the operation 
  • TDS - 1 config. over all the operation (elec. data only)
  • BIAS ON - single-ended signal on each antenna. Biasing disabled
  • THR — 2 config.  = 1 before/after (10 min.) + 1 during deployment.

→ THR will lead the overall timeline of the deployment

THR requests to have 3 PA HF ON (cf. action EL about risk with PA heating above)

  • Action XB : send an email to Sylvain Lodiot to ask if SBM event data can be downlinked during NECP

2. ANT calibration rolls (RPW-4)

  • SBM_DETECTION submode for all
  • BIAS ON with biasing disabled 
  • All sub-systems with 1 config. overall the operation
  • May be run during first E-GAM (end of CP) instead of NECP

2. SCM calibration operation (RPW-5)

  • No specific request SBM_DETECTION or NORMAL mode ok for all the teams → SBM_DETECTION
  • All sub-systems with 1 config. overall the operation
  • Might be run during first E-GAM (end of CP) instead of NECP

2. In-flight inter-instrument interference campaign (RPW-6)

  • RW filtering - probably when EMC with platform - LFR 2 config ENABLE/DISABLE filtering

2. RPW PAS filtering tune campaign (RPW-7)
  • LFR 2 config. ENABLE/DISABLE PAS-filtering
  • PAS ON 
  • Planned specific telecon with PAS? cf. CNES 

3. Discussion of cruise phase configuration : low rate config
  1. XB: Send the new "RPW_NECP_V2.xlsx" before  
4. Action-items, organization and planning


  1. XB: Send info about next telecon.