Goals

  • RPW Operations Board (ROB) telecon

Date

at 3pm

Attendees



Agenda

  1. Status & update on the Commissioning configurations

  2. ROB organization

  3. Next telecon

  4. AOB

Discussion items

ItemNotesAction-Items
1
  • Comments from Xavier:
    • First draft of the payload commissioning planning has been sent to the instrument teams (IT) as an Excel file. Xavier has fowarded the Excel file to the ROB (a copy of the file is also attached at the bottom of this page). The MOC asks to IT to send feedbacks before .
    • Sylvain Lodiot (MOC) has confirmed that it should be possible to downlink SBM data during commissioning (see action ROCOPE-225 - Getting issue details... STATUS )
  • RPW-5 (RPW-5: SCM Noise Measurement Campaign)
    • Xavier highlights that the RPW-5 activity cannot be performed during the commissioning phase. On the MOC planning, it is planned on , but the S/C is supposed to cross the Earth lobes on  according to Olga's computation (see SCM Noise Measurement Campaign Operation Plan), which is one day after the launch! It will be thus ask to MOC to remove this activity from the commissioning planning and to shift this operation during the Earth flyby (planned ~1.5 year after launch, just before the start of the nominal phase in the 2020 Feb. launch scenario).
    • Xavier reminds that although the RPW-5 activity is postponed, we still need to provide the associated TC sequences to MOC before the end of 2018! Both RPW TC sequences for Near Earth Commissioning Phase (NECP) and Cruise  Phase (CP) shall be delivered to MOC and tested during SVT1 next year.
    • Matthieu proposes to no use SBM_DETECTION mode, since it will be difficult to retrieve SBM1 data during this operation. ROB members agree with this proposition and SURVEY_NORMAL mode will be then used.
  • RPW-3 (RPW-3: RPW Antennas Deployements)
    • Magnetic field measurements will be available
    • Issue concerning the PA HF ON/OFF is still open (see action ROCOPE-222 - Getting issue details... STATUS )
  • RPW-1 (RPW-1: First Instrument Switching-on)
    • Waiting for inputs from CNES (see action ROCOPE-224 - Getting issue details... STATUS )
  • RPW-7 (RPW-7: RPW - PAS filtering tune campaign)
    • Waiting for inputs from CNES (see action ROCOPE-226 - Getting issue details... STATUS )
  • RPW-8 (RPW-8: RPW Nominal Working Rehearsal)
    • Main goal of this activity is to run all of the RPW and other In Situ (IS) instruments (SWA, MAG and EPD) in the NORMAL mode (nominal "default-science" configuration) for at least 24h.
    • This new activity shall be requested for commissioning before the MOC deadline on .
    • Xavier thinks that other IS instrument teams should at least be informed about this request before the deadline.

  • A first set of RPW TC sequences for NECP and CP will be sent within few days to MOC by Diane and Antonio. According to MOC, the last chance for sending RPW TC sequences for commissioning is the end of 2018.
  • Xavier highlights that teams must also send asap to the ROC (Diane, Antonio and Xavier) their needs concerning any regular TC execution to be performed in the RPW nominal operations timeline. For instance, TDS team has requested to have at least every month a TDS diagnosis (i.e., execute the TC_TDS_PERFORM _DIAGNOSIS). Additionaly, for now the ROC planned to run the following operations every week: Bias sweeping/calibration, SCM/LFR calibration, THR calibration, Bias current setting, TDS TSWF dumping (and SBM data downlinking requests). Do the teams need other extra regular operations? These operations must also have specific TC sequences.
  • Low rate configuration
    • Jan would like to slightly increate the TDS TM contribution to the low rate
    • Jan will send to Diane and Antonio his tailored version of the low rate calculator Excel file, containing proposed upgrade
    • Diane and Antonio will then update the configuration and corresponding sequences
  • ROB: send any feedback to Xavier about the commissioning planning before the deadline. ROCOPE-228 - Getting issue details... STATUS
  • ROB: indicates to ROC (Diane, Antonio and Xavier) where they expect to retrieve SBM1 data during each commissioning operations ROCOPE-229 - Getting issue details... STATUS
  • Xavier: Say to MOC that the RPW-5 will be postponed to the E-GAM1 ROCOPE-230 - Getting issue details... STATUS
  • Milan: inform other IS teams about the RPW-8 activity request before the deadline. ROCOPE-231 - Getting issue details... STATUS
  • Xavier: Send request to MOC about adding RPW-8 activity ROCOPE-232 - Getting issue details... STATUS
  • ROB : send to ROC (Diane, Antonio and Xavier) any request concerning specific TC executions to be performed regularly during CP/NMP timeline. ROCOPE-233 - Getting issue details... STATUS
  • Jan: Send to Diane and Antonio his upgraded version of low rate calculator ROCOPE-234 - Getting issue details... STATUS
  • Diane/Antonio: From Jan low rate calculator Excel, update low rate configuration and sequences. ROCOPE-235 - Getting issue details... STATUS
2.
  • Milan has organized this first telecon, but Jan will be the chair for the next ones.
  • Jan highlights that ROB telecon meeting notes should be archived. Xavier propose to save them on the ROC Confluence. He will prepare the meeting note for this telecon.
  • Xavier will prepare meeting notes for the telecon.
3.
  • Jan will send a Doodle poll to find a date for the next ROB telecon. (Should be planned if possible before the   MOC deadline)
  • Jan: send a doodle poll for the next ROB telecon.