Dateoct. 12, 2017
Demandes
Getting issues...


Context

Preparation of the SVT1 datapackage release for RPW.

The SVT1 campaign is expected to occur between Feb. to May 2019 (TBC). It will be driven by MOC from ESOC site (Darmstadt, Germany). The RPW PFM model integrated on the S/C will be used for the test.

No specific equipment is requested to the instrument teams (IT) to perform the test. MOC will use its own infrastructure.

The ROC team will have to deliver the SVT1 datapackage, then support the MOC team in the preparation, execution and analysing of the test. Presence of ROC team at ESOC during test is TBD.

Test plan and report will be written by the MOC. ROC will participate to the possible anomaly investigations related to RPW. A ROC internal test report for SVT1 will have to be written and stored in the ROC document managenemtn system (https://ged.obspm.fr/j_obspm/docbase/topic/browse_classic?topicID=T80) at the end.

Interlocutors are:

  • Sylvain Lodiot at MOC

Main features of the SVT1 datapackage

  1. Upgraded RPW flight procedures from IGST42 datapackage
  2. New RPW flight procedures related to the instrument commissioning and cruise phase operations.
  3. Upgraded version of the RPW ISM
  4. First issue 1.0 of the RPW flight configuration description document (FCDD)

Planning

  • A first set of RPW flight procedures for SVT1 is planned to be delivered by email to Sylvain Lodiot (MOC) on mid-October 2018.
  • The full SVT1 data package will have to be delivered before .

Action-items related to the SVT1 datapackage

Key Summary T Created Updated Due Assignee Reporter P Status Resolution