Tests should be run during the RSS3VC planned December 17 to 21, 2018.
After verification, resulting L1/HK CDF will be available from the ROC Web site (private area).
Integration tests of RCS software into the ROC pipelines will start on spring 2019. Each team will be contacted individually. The integration should be done in the following order (TBC) :
THR_CALBAR
TDS_CALBA
LFR_CALBUT
SCMCAL
BICAS
A specific pipeline instance will be deployed on the roc-dev server by ROC to test the RCS interface compliance. This instance will be available for teams. The ROC will provide an up-to-date issue of the associated use manual on January 2019.
RCS "ready-for-flight" software versions (full processing+RCS ICD compliance) are supposed to be ready by end of April 2019.
Priority is given to the RODP now. Nevertheless, the ROC also wants to test the RCS integration and run into the pipeline (for ROC-SGSE, RCS execution is the same expect that the descriptor and CDF skeletons are different).
ROC-SGSE will be also used during the SolO mission to perform operations tests and anomaly investigation with LESIA GSE (EM1 or EM2) on-ground.