Goals

  • RPW Operations Board (ROB) telecon

Date

at 2pm

Attendees


Agenda

  1. RPW status update

  2. HK period during comissioning

  3. Data coordinate systems/reference frames

  4. Data validation organization
  5. Instrument paper
  6. Review of actions from the last consortium meeting.
  7. Next ROB telecon & AOB

Discussion items

ItemNotesAction-Items
1

Milan's report:

    • RPW status overall good, TVAC passed, preparing for vibrations, Feb. 2020 still seems realistic.
    • More damage to instruments during AIT (MAG harness damaged this time).
    • All 3 RPW antennas installed. Damaged heatshield replaced.

2.

HK period during comissioning:

  • Diane's proposal was to increase the period of HK generation during housekeeping to 1 second.
  • TM bandwidth required for 1 second HK not negligible, but very small.
  • The proposal was agreed unanimously.

3.

Coordinate systems for L2 science data:

  • Baseline (already discussed at consortium meeting in Dresden): use both RTN and instrument coordinates.
  • In some cases, instrument coordinates are the only choice (e.g. SCM B_MF data).
  • Xavier considers having two coordinate systems space inefficient, proposes to include a transformation matrix instead - at least in some cases.
  • PSP FIELDS use RTN (TBC)
  • Jan to check with MAG
Jan: Check with Tim Horbury what coordinate system is used by MAG.
4.

Science data validation organization:

Everyone to check DVVP and provide feedback to Xavier.
5.

Instrument paper:

  • Paper is now 60% complete
  • We are late, but not critically, we are not the worst in the class (yet).
  • Most contributions from team received, Andris will send his in ~2 weeks
  • Milan will send around the next draft by end January.
Milan to send the instrument paper draft.
6.

Review of action items from last consortium meeting.

Actions from consortium meeting #21 (Dresden) here:

20_RPW#21_June2018_Maksimovic_instrumentPaper_Science_Actions.pdf




7.

AOB: SOWG at ESAC 21-23 January. Milan, Xavier and Jan (+ CNES representatives) will go.

Next telecon: February 22, 2019 14:00 CET


Action items

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Attached items

Data Validation and Verification Plan (draft sent by Xavier):

ROC-GEN-SCI-PLN-00077-LES_Iss01_Rev00(RPW_DVVP).draft-2019011.pdf

Presentation on DVVP (by Xavier):

roc_rpw_science_dvvp-overview_v01.pdf