This page gives information about the RPW Flight Procedures (RFP).


About the RPW Flight Procedures

According to the FOP, the flight procedures are divided into three categories: the Flight Control Procedures (FCP), the Contingency Recovery Procedures (CRP) and the Commissioning Procedures (COM).

The RPW procedures files are archived in the /Procedures folder of the https://gitlab.obspm.fr/ROC/OpsLib gitlab repository (restricted access). A test version of this repository is available in https://gitlab.obspm.fr/ROC/OpsLib-Test (restricted access).

For a list of the corresponding RPW Operating Plans (ROP), see RPW Operating Plans.

For the tansition matrix giving the ROP versus procedures.

For each of these categories, a table is given with the following columns:

  • Name – Name of the procedure (according to the ESA convention)
  • Description - Short description of the procedure (to be reported into the info sheet of the Excel export)
  • State at start (i.e., initial ROP)
  • State at end (i.e., final ROP)
  • Author(s) – Entity that creates the procedure
  • Total duration – Total duration of the procedure in seconds (including the minimal time delay to be let after the last TC execution)
  • Minimal time delay at the end - Minimal time delay in seconds to be let at the end of the procedure execution (i.e., to be let after the last TC execution)
  • Status – Status of the procedure writing (i.e., "Done", "In Progress", "To Be Done", "Validated", "To Be replaced")

Editing a procedure

The SOC provides to the instrument teams an online "Procedure Builder" than can be used to create/edit procedures. The site dedicated to RPW is available here. Nevertheless, the SOC cannot guarantee that this tool will be maintained during the whole mission, and the instrument teams are invited to develop and maintain their own tool. In the case of the ROC, the FIGARO tool, accessible via the MUSIC Web portal will replace at medium term the SOC procedure builder.


IMPORTANT

Please visit the operation guidelines page before editing a procedure!

Flight Control Procedures (FCP)

The table below gives the list of generic procedures, other than specific to the contingency recovery or commissioning operations (see next sections).


NameDescriptionState at startState at endAuthor(s)Total duration (s)StatusComments

IW-FCP-001


RPW switch ON in SAFE mode using the prime/A interface for LCL and SpaceWireRPW_OFFRPW_SAFE_PRIME-A
Done
IW-FCP-002RPW switch ON in SAFE mode using the prime/B interface for LCL and SpaceWireRPW_OFFRPW_SAFE_PRIME-B
Done
IW-FCP-011Start DAS from EEPROM1 and transition to SERVICE modeRPW_SAFERPW_SERVICE
Done
IW-FCP-012BOOT LFR from EEPROM1 + Disabled Verif BootRPW_SERVICERPW_SERVICE
Done
IW-FCP-013BOOT THR from EEPROM1 + Disabled Verif BootRPW_SERVICERPW_SERVICE
Done
IW-FCP-014BOOT TDS from EEPROM1 + Disabled Verif BootRPW_SERVICERPW_SERVICE
Done

IW-FCP-015

Switch ON BIASRPW_SERVICERPW_SERVICE
Done
IW-FCP-016PA Switch ONRPW_SERVICERPW_SERVICE
Done
IW-FCP-017Switch on converterRPW_SAFERPW_SERVICE
Done
IW-FCP-018SCM switch ONRPW_SERVICERPW_SERVICE
Done
IW-FCP-030Configure TDS, LFR and THR for the RPW_SCIENCE-NORMAL_DEFAULT config.RPW_SERVICERPW_SERVICE
DoneIW-FCP-001 to be renamed to IW-FCP-009
IW-FCP-031Configure the Bias for the RPW_SCIENCE-NORMAL_DEFAULT config.RPW_SERVICERPW_SERVICE
DoneIW-FCP-002 to be renamed to IW-FCP-009
IW-FCP-032Enter in RPW_SCIENCE-NORMAL_DEFAULTRPW_SERVICERPW_SCIENCE-NORMAL_DEFAULT
DoneIW-FCP-003 to be renamed to IW-FCP-009

IW-FCP-033

Configure and execute the BIAS sweepRPW_SCIENCERPW_SCIENCE2501Done
IW-FCP-034 Internal Calibration for LFRRPW_SCIENCERPW_SCIENCE600Done
IW-FCP-035Enter in RPW mode safeRPW_SCIENCERPW_SAFE
Done
IW-FCP-036BIAS CalibrationRPW_SCIENCE380
IW-FCP-037Enter in RPW_SURVEY-BURST_DEFAULTRPW_SCIENCERPW_SCIENCE-BURST_DEFAULT
Done
IW-FCP-038Configure TDS, LFR and THR for the RPW_SCIENCE-BURST_DEFAULT configRPW_SERVICERPW_SERVICE
Done
IW-FCP-039Configure DPU and DAS + configure HK periodRPW_SAFERPW_SERVICE
Done
IW-FCP-040LOAD TDS, LFR common parametersRPW_SERVICERPW_SERVICE
Done
IW-FCP-041Configure TDS, LFR for sbm1 modeRPW_SERVICERPW_SERVICE
done (temporary)
IW-FCP-042Configure TDS, LFR for sbm2 modeRPW_SERVICERPW_SERVICE
done (temporary)
IW-FCP-043Configure TDS LFM parametersRPW_SERVICERPW_SERVICE
done (temporary)
IW-FCP-044 Configure internal Calibration for THRRPW_SERVICERPW_SERVICE
done
IW-FCP-045

DUMP configurations and clear all the counters and statistic information in the DAS HK reports

RPW_SERVICERPW_SERVICE
done
IW-FCP-027xxEnter in RPW_SURVEY-BURST_TDS_single_endedRPW_SCIENCE
In progress
IW-FCP-028xxEnter in RPW_SURVEY-BURST_TDS_dipoleRPW_SCIENCERPW_SCIENCE
In progress
IW-FCP-029xxEnter in RPW_SURVEY-BACKUP(through RPW Service mode)RPW_SERVICERPW_SCIENCE-BACKUP
In progress
IW-FCP-030xxFix the current value on BIAS 1,2,3RPW_SCIENCERPW_SCIENCE
Done
IW-FCP-XXXEnter in RPW STANDBY modeRPW_SAFERPW_STANDBY

To be done
IW-FCP-XXXEnter in RPW STANDBY modeRPW_STANDBYRPW_SAFE

To be done
IW-FCP-XXXEnter in RPW SERVICE mode from the RPW SCIENCE modeRPW_SCIENCERPW_SERVICE

To be done

Contingency Recovery Procedures (CRP)

The table below gives the list of procedures specific to the contingency recovery operations.

NameDescriptionConfiguration at startConfiguration at endAuthor(s)Creation dateStatusComments








Commissioning Procedures (COM)

The table below gives the list of procedures specific to the commissionning operations, including ANT and iBoom deployments, as well as the interference campaign.

NameDescriptionConfiguration at startConfiguration at endAuthor(s)Creation dateStatusComments









Action Items

Action items relative to the flight procedures

#DescriptionAssigneeCommentIssueDone
1IW-FCP-021: TNR-HFR must be set in specific mag. config during the LFR calibration, in order to check B measurements

  •  
2Identify formal parameters for each procedure

  •  
3Check that expected TM are provided in procedures (e.g., Ack., dump, etc.)

  •  
4Merge procedures that can be run with formal parameters (e.g., EEPROM1/EEPROM2/RAM loading, PRIME-A/PRIME-B, etc.)

  •  
5

Complete the document of Sylvain Lodiot about the instrument state model (see document "rpw.docx" attached below). Especially see for the power (for STANDBY mode, need to split)



  •  

Attached Items