Discussion items

ItemNotesAction-Items
1.
  • Requirements and scope (introduction)
    • See slide 3 in RPW_FSW_Upgrade_Support_20201130_V01.pdf attached below
  • MOC needs and recommendation
    • See slide 4 in RPW_FSW_Upgrade_Support_20201130_V01.pdf attached below
  • DAS FSW needs and resources
    • No need to update DAS
    • LESIA DAS team will retrieve the FSW patch images from analyser teams, perform usual verifications (image size, consistency w.r.t. to budget, memory resource on EEPROMs) and provide to the ROC the FSW patch commands as TcScript files.
    • It is important the analyzer teams check memory footprint (shall remain in the budget)
  • TDS FSW needs and resources
    • See td_software_plans.pdf attached below
    • 2-3 months of work
    • No need specific funding or external human resource
    • Leads by Jan and Ludek
    • No need to update TM/TC
  • LFR FSW needs and resources
    • See LFR FSW upgrade_30 november 2020.pdf attached below
    • At least 6 montshs of work
    • No need specific funding or external human resource, except maybe for quality support. CNES may supply software quality support (Charles Dixon will be in charge of the software quality assurance from CNES in 2021)
    • Leads by Thomas and Bruno (with Alexis and Veronique in the loop)
    • No need to update TM/TC, but might require to change descriptions in the ICD (not a problem for Philippe → will no impact IDB structure)
    • May need to inject stimuli during validation tests on GSE at LESIA
  • THR FSW needs and resources
    • See THR_FS_Upgrade_30112020.pdf attached below
    • At least 3 months of work
    • Need funding for THR FSW upgrade cause K.Boughedada left the team (and quality support? → Check if possible with W.Recard from NEXEYA). Funding from LESIA RPW?
    • Leads by Milan, Pierre-Luc, Antonio and Moustapha
  • ROC needs and resources
    • No need extra funding or resources
    • Leads by Xavier and Diane
    • Will coordinate the activity (main contact with the MOC/SOC)
    • Will perform validation tests on GSE at LESIA and prepare the PDOR/MDOR for the MOC (Patching + SFT)
    • Prepare FSW patch plan and report
  • Desi - Check if CNES can supply support for FSW quality
  • Xavier - Check with Philippe about quality support at LESIA for THR FSW upgrade
  • THR Team - To supply to the Xavier the detailed needs (human and funding) for the FSW upgrading
2.
  • See slide 5 in RPW_FSW_Upgrade_Support_20201130_V01.pdf attached below
  • Validation test will be performed by the ROC with the support of the teams on the GSE at LESIA
  • LFR team - To confirm the need of stimuli for validation tests on the GSE and provide, if needed, the stimuli files
  • ROC (Xavier and Diane) - Check if stimuli can be injected in the EM2 with the GSE at LESIA
  • ROC (Xavier and Diane) - Check with Sylvian Lodiot and/or Julian Braun about verification/validation steps at MOC level (only MDOR/PDOR consistencies?)
  • LFR
    • Status report: see attached slides below (FSW_update_progress_10_02_2021.pdf)
    • Important upgrade (needs deep investigations in terms of CPU budget and data on-board processing)
    • Current GSE needs upgraded. (Philippe warns that the LFR GSE should not be significantly upgrades to avoid introducing regressions).
    • No impact on IDB or FOP
    • Running stimuli on MEB EM2 at LESIA requested
    • Need to quantify the need in terms of QAP support
  • TDS
    • Status report: see attached slides below (tds_software_feb10.pdf)
    • Might require to update IDB / FOP (enumeration / range to be changed)
  • THR
    • Minor upgrade
    • 3 months of work is expected to prepare THR FSW patch
    • No impact on IDB or FOP
    • Running on MEB EM2 at LESIA requested.
      • Before patch final delivery to FSW team, in order to:  try to reproduce the TNR delta time issue (at least one day of run is needed to have a chance to see the error). Check for plasma peak on-board algorithm with stimuli.
    • Need to quantify the need in terms of QAP support
  • ROC
    • Need to schedule the run on the MEB EM2 (for THR/LFR FSW testing, then to test command/control FSW patching before delivery to ESA)
  •  Xavier/Diane to inform Simone  Thjis about planning (add her in the loop for MEB EM2 runs) - Before next telecon
  •  Jan to see if IDB changes are really needed or can be avoided. - Before next telecon
  •  LFR and THR teams: to send to Charles Dixon and Desi Raulin the needs for QAP support - Before next telecon
2.
  • TDS and THR teams think to be ready for FSW on-board patching on October 2021
  • LFR team will need more time. Need to re-schedule a second patching on the 2022, first semester (to be confirmed by LFR before the end of the year).
  • ROC needs to inform MOC/SOC about latest plans
  •  Xavier sends a message to MOC/SOC to keep them informed about plan - Before next telecon
  •  Xavier/Diane to write a first "RPW FSW patching plan" detailling the needs, actors and planning - Before next telecon
  •  LFR team to refine the date of delivery for its patch in 2022 - End of 2021
3.
  • Next meeting planned on March 17 at 10AM (CET)
3.
  • ROC - To inform the MOC/SOC about preliminary schedules and the possibility to perform the patches around the planned dates
4.
  • Add Alexis Jeandet and Bruno Katra in the working group mails