Status of delivery and outstanding engineering issues for the RPW Calibration Software (RCS).
Introduction
This page presents the delivery status of the RCS-related software, data products and documentation.
The mechanism to deliver RCS components is described in the ROC Engineering Guidelines for External Users (REGU) - ROC-GEN-SYS-NTT-00019-LES: (see latest issue available in ROC Documents).
RCS activity-related meeting notes are available in RCS Meeting Notes.
List of action-items is given at the bottom of the page.
RCS deliverable status
RCS data products
Deliverables | TDS | LFR | THR | SCM | Bias |
---|---|---|---|---|---|
ROC-SGSE L1R CDF skeletons | Delivered on gitlab | Delivered on gitlab | N/A | N/A | N/A |
ROC-SGSE L1R CDF test data | |||||
ROC-SGSE L2S CDF skeletons | Delivered on gitlab | Delivered on gitlab | Delivered on gitlab | Delivered on gitlab | Delivered on gitlab |
ROC-SGSE L2S test data CDF | |||||
ROC-SGSE CAL table CDF skeletons | Delivered for LFM and SURV-SWF | V1 delivered | To be delivered | V1 delivered | V01 delivered |
ROC-SGSE CAL table CDF | To be delivered | Delivered on gitlab | To be delivered | V1 delivered | To be delivered |
SOLO RPW L1R CDF skeletons (for RODP) | To be delivered | To be delivered | Do we need L1R for THR? | ||
SOLO RPW L1R test data CDF (for RODP) | |||||
SOLO RPW L2 CDF skeletons (for RODP) | Need updates (cal. metadata, ANC data and attributes for mission) | Need updates (cal. metadata, ANC data and attributes for mission) | Need updates (cal. metadata, ANC data and attributes for mission) | Need updates (cal. metadata, ANC data and attributes for mission) | Need updates (cal. metadata, ANC data and attributes for mission) |
SOLO RPW L2 test data CDF (for RODP) | To be produced | To be produced | To be produced | To be produced | To be produced |
SOLO RPW CAL table CDF skeletons (for RODP) | To be delivered | To be delivered | To be delivered | To be delivered | To be delivered |
SOLO RPW CAL table CDF (for RODP) | To be produced | To be produced | To be produced | To be produced | To be produced |
RCS software delivery status
Software version | Due date | TDS | LFR | THR | SCM | Bias |
---|---|---|---|---|---|---|
RCS preliminary S/W (preliminary ROC-SGSE data processing for ground calibration campaigns) |
| |||||
RCS "partial processing" S/W (preliminary L1R/L2S data production) for RSS3_0 release |
| 0.8 pushed on Gitlab | 0.3 pushed on Git (master branch) | 1.1.0 pushed on Gitlab (develop branch) | 0.6 pushed on Gitlab (master branch) | 0.1.0 pushed on Gitlab (master branch) |
RCS "full processing" S/W (full L1R/L2S data production + partial L2) for RSS3 release |
| 0.7 pushed in Gitlab | ||||
RCS "ready-for-flight" S/W (full L1R/L2S/L2 data production + ICD compliant + test data) for RSS4 release |
| |||||
RCS "fully operational" S/W (updgrades after commissioning) for RSS5 release |
|
RCS documentation delivery status
Document | TDS | LFR | THR | SCM | Bias |
---|---|---|---|---|---|
SRS | 1.0 delivered | 1.0 delivered | 1.1 delivered. | 1.0 delivered | |
SUM | 1.0 delivered | 1.2 delivered | 1.0 delivered. | Draft version delivered |
Color cell legend
OK | Incomplete | Not OK | N/A |
Action-Items summary list
TO BE DONE TASKS
TDS
LFR
SCM
BIAS
THR
ROC
TO BE ADDED TO JIRA
Update the ROC-SGSE documentation to remove the reference to L2R and replace it by the L1R – Xavier Bonnin–
Produce ROC-SGSE V3 L1/HK for all campaigns (EM2 BLANK TESTS, PFM CAL and DELTACAL) – Xavier Bonnin– – postponed due RODP/ROC-SGSE plugin merging
- Provide the list of L1/HK quicklook data products for the SOLO mission -- ROC – – To be provided into the "RPW data products" doc.
- Update the RCS ICD validation tool on roc-dev – – Quynh Nhu NGUYEN
- After received example of cal. tables, ROC will make proposal of conventions for the CAL table. It will be written in the "RPW Data Products" – Xavier Bonnin – ASA examples have been received
- Plan a discussion about L3 data exchange – Xavier Bonnin –