Goals

Date

at 10PM (via ZOOM)

Attendees


Agenda

  1. Review of action-items and open issues (by each team: TDS, LFR, THR, ROC, DAS)
  2. Planning
  3. Next meeting
  4. AOB

Discussion items

ItemNotesAction-Items
1.
  • LFR
    • ASM bug has been solved, but S/W crashes (new computation in S/W seems to be too heavy for CPU load. Work is still in progress
    • QAP support:
      • Required support needs to be refine with help of the CNES, as well as budget
      • May be approx. 5-6 days of NEXEYA support
      • Joined effort with LESIA is probably not needed, since the degrees of quality support should be not the same (less for LESIA)
  • TDS
    • A new version of the TDS software will delivered
    • TDS should be OK to deliver a FSW image before mid-July 2021
    • Upgrades seem to be OK (need verifications)
    • Not important changes, increases by few bytes the software size
    • LeeRoy thinks it will be OK to deliver corresponding C-SGSE scripts to ROC by the end of August.
  • THR
    • FSW upgrades
      • Science algorithm of new THR FSW has been tested by Pierre-Luc
    • FSW tests
      • C-SGSE scripts RPWDPU-1984_Load_EEPROM1_RpwThrApp_V3_6_1_0 and RPWDPU-1984_Load_EEPROM2_RpwThrApp_V3_6_1_0 available on RPW-AIT2AI
      • Scripts to be run by ROC
      • Kamel will be at LESIA from July 5 to 9 to test and finalize the THR patch. It can be good that both ROC and DAS teams are available if required.
      • ROC will try to see with Simone Thjis if it is possible to test the execution of the C-SGSE scripts before the Kamel's arrival (TBC)
      • New TNR tests on EM2 perfomed by ROC at LESIA. Data sent to Antonio
    • QAP support
      • Light support needed for LESIA.
      • THR team will see with CNES about quantifying support from NEXEYA and the impact on the FSW upgrade on documentation.
      • Planned a discussion about documentation between THR team and Charles Dixon, if possible, during the week when Kamel is at Meudon.
    • Documentation:
      • Kamel might write the documentation
      • What about THR test plan ? See with ESA (if all tests in plan are not run, it shall be justified)
    • If everything is OK,  new THR FSW image might be delivered before mid-July
  • ROC
    • Will support THR team for the tests run when Kamel will be here
    • Still need to write formal plan in preparation to in-flight patching operation
    • MOC/SOC will have to be informed if current planning is changed
    • Main activities are still planned on Sept/October (retrieve C-SGSE scripts, test on EM2 and convert into MDOR/PDOR)
  • THR team to think about who will update the documentation related to FSW patching
  • ROC (Xavier/Diane) to write a  "RPW FSW patching report" detailling the tests results - To be joined with teams' documents to the datapack delivered to ESA
  • Xavier to see if joint effort is possible about QAP support for LPP and LESIA
  • LeeRoy: To check availability during July 5 to 9 (in case of C-SGSE script re-delivery)
  • ROC to run with the help of Simone the THR C-SGSE scripts on EM2
2.
  • TDS/THR FSW images delivered on mid-July 2021 to DAS team
  • DAS team to deliver to ROC C-SGSE scripts (deadline mid-september 2021)
  • LFR team to refine the date of delivery for its patch in 2022 - End of 2021
3.
  • Next meeting planned on September 14 at 10AM (CEST)

4.